KLIA aerotrain to be completed by end-Jan 2025, 2 months ahead of schedule

New aerotrains from China expected to arrive by end of Q3 this year, says MAHB.

Updated 2 years ago · Published on

KLIA aerotrain to be completed by end-Jan 2025, 2 months ahead of schedule
A view of Kuala Lumpur International Airport. – The Vibes file pic, June 18, 2024.

KUALA Lumpur International Airport’s (KLIA) aerotrain project is expected to be completed by January 31, 2025, ahead of the project’s originally planned completion date, said Malaysia Airports Holdings Bhd (MAHB).

The new completion date was finalised through a contract signed on June 14, 2024 between its subsidiary Malaysia Airports (Sepang) Sdn Bhd and Alstom Transport Systems (Malaysia) Sdn Bhd, as well as a joint venture consisting of IJM Construction Sdn Bhd and Pestech Technology Sdn Bhd.

It said MA Sepang is a wholly-owned subsidiary of MAHB and Alstom Transport Systems (Malaysia) Sdn Bhd (Alstom).

“This advances the original completion date of March 31, 2025, by two months.

“As the project coordination lead, MAHB Alstom will oversee the delivery of three new trains, the upgrading of two lines, and the overall comprehensive testing required for safe operation,” it said in a statement today.

MAHB said that according to the project’s timeline, the new aerotrains are expected to arrive in Malaysia from China by the end of the third quarter of this year.

“The aerotrains will then undergo commissioning and rigorous testing by the relevant authorities before official operations can commence,” it said.

In March 2022, MAHB announced the awarding of the KLIA aerotrain replacement project with a scheduled completion timeline of three years. 

A delay in the project, however, led MAHB to terminate the contract.

A new project was awarded in January 2024 to a consortium comprising Alstom, the aerotrain’s original equipment manufacturer, and IJMC-Pestech JV to steer the project back on track.

MAHB acting group CEO Rastam Shahrom pointed out that the project completion ahead of schedule was a testament to the relentless commitment to improving the passenger experience. – June 18, 2024

Related News

Malaysia / 1w

More than RM8m drugs seized at Penang airport this year

Malaysia / 1mth

Mohd Shuhaily pleads not guilty to assaulting 2 cops

Malaysia / 2mth

Negeri Sembilan SUK declines to gazette proclamation removing Tuanku Muhriz

Malaysia / 2mth

Tuanku Muhriz return puts Negeri Sembilan royal dispute in focus

Malaysia / 3mth

Cabinet approves 17 measures to beef up KLIA security checks, controls

Malaysia / 3mth

Disturbed woman at KLIA taken to hospital, had forgotten to take medication

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Business

Oil retreat offers limited relief as ringgit weakens against firmer US dollar

Business

Oil origin claims need official documents, not trader papers, says expert

Business

Pengerang needs to create wider economic value, not just store more oil, says expert

Business

Three Malaysian firms placed on US trade blacklist over advanced technology diversion fears

Business

Oil extends losing streak for fourth week as supply glut outweighs Middle East tensions

Business

Matrix Concepts ranked among top ten developers at TDPA 2026

Business

Govt moves to block seven US-blacklisted entities from accessing local data centres

Business

NexG share surge puts spotlight on RM7.5b takeover proposal as SC examines trading