Labuan contractors facing building materials shortages, govt projects at standstill

Change in export policy, closure of quarries due to Covid-19 driving angst among contractors

Updated 5 years ago · Published on

Labuan contractors facing building materials shortages, govt projects at standstill
The Labuan G1 Contractor Association says that building material importers now must use the K2 form – instead of the K3 form previously – and approval process is causing delays. – The Vibes file pic, November 10, 2021

LABUAN – Contractors across this duty-free island are struggling to take advantage of the reopening of the economy, as rising costs and the lack of building materials are threatening their business operations.

Local contractors here lamented that the increasing cost of building materials due to supply shortages is the biggest concern for their project management plans.

Labuan G1 Contractor Association president Chemat Mustapha said the lack of availability of building materials such as cement and stones was due to the recent review of export policy from Sabah and the closure of quarries due to the Covid-19 pandemic on the mainland.

“On the issue of stone supply, the Sabah Government needs a permit (issued by the Ministry of Energy and Natural Resources) from the main supplier before the supply is permitted to be exported to Labuan… the issuance of the permit takes time and (this) causes the delay in supply to Labuan,” he told Bernama.

Chemat said the new stone export policy to Labuan took effect in October this year.

“Prior to the review, Labuan importers (building materials companies) are using the K3 customs declaration form (Transportation of Goods Between Peninsular Malaysia, Sabah and Sarawak and transportation within the same territory).

“But now (effective October), they are required to use the K2 form – for export of goods from the country, of which the process of approval takes time… many government projects come to a standstill due to this delay,” he said.

Chemat also urged the Public Works Department to review the price of the project tender to account for the rising cost of building materials.

A local contractor, Sophian Said, said the unavailability of these building materials had caused his company’s projects to come to a standstill.

“The price of raw materials is rising dramatically, and traditional fixed-price contracts are not designed to account for this new reality,” he said.

Sophian said this trend is expected to continue until next year and would impact not only cost but also lead times, which subsequently would cause project delays and a difficulty in meeting scheduled requirements. – Bernama, November 10, 2021

Related News

Malaysia / 6h

Govt approves RM451m for projects in 66 opposition-held constituencies

Heritage / 5d

No development at Mount Erskine burial site: land is for cemetery-related purposes

Events / 2w

Penang launches its Smart City Blueprint 2040

Community / 4w

Paya Terubong landslide: Resident writes to 15 ADUN to seek ban on hillslope development

Malaysia / 2mth

Indian community will never be marginalised in development agenda – PM Anwar

Business / 2mth

Robo.ai swings to positive equity after US$46.7m first-half profit

Spotlight

Malaysia

Durian trader in Raub loses nearly half a million in AI-based investment

Malaysia

GPS banks on fresh faces, retains Abang Johari and key incumbents for Sarawak polls

Malaysia

Anwar yet to accept Anthony Loke's resignation, says DAP chief remains on leave

Business

MAG to add 10 Boeing Dreamliners in long-term fleet expansion drive

Malaysia

Court imposes gag order in case against AKPS chief Mohd Shuhaily

Malaysia

Cyber scam losses hit estimated RM19.7b in a year

Malaysia

Govt approves RM451m for projects in 66 opposition-held constituencies

By Alfian Z.M. Tahir

You may be interested

Business

MAG to add 10 Boeing Dreamliners in long-term fleet expansion drive

Business

Matrix Concepts founder honoured as FIABCI Malaysia Property Man of the Year 2026

Business

Three Malaysian firms placed on US trade blacklist over advanced technology diversion fears

Business

Oil prices holds above US$80 as Hormuz attacks heighten supply concerns

Business

Pengerang needs to create wider economic value, not just store more oil, says expert

Business

South Korean robotic parking company explores opportunities in Malaysia

By Ian McIntyre

Business

NexG share surge puts spotlight on RM7.5b takeover proposal as SC examines trading

Business

Oil retreat offers limited relief as ringgit weakens against firmer US dollar