BDB to complete phase one of Langkawi Premium Outlet in Oct

Phase two to be ready in 2024, covering 17.4ha, says company chairman

Updated 4 years ago · Published on

BDB to complete phase one of Langkawi Premium Outlet in Oct
Company executive chairman Che Had Dhali 36 out of 38 units in Langkawi Premium Outlet (LPO) have been rented to local entrepreneurs. – Bina Darulaman Bhd Facebook pic, June 29, 2022

KUALA LUMPUR – Bina Darulaman Bhd (BDB) is expecting phase one of Langkawi Premium Outlet (LPO) to be ready by the end of October.

BDB executive chairman Che Had Dhali said the project is 95% completed.

“I am very happy about the impending opening of the project, and that 36 out of 38 units in LPO have been rented to local entrepreneurs which is a good achievement for BDB,” he said during a visit to Wisma Bernama here today.

At the same time, he said phase two of the project is expected to be ready in 2024 covering an overall area of 17.4ha.

“Now, we are using more than 10% of the land to accommodate 38 units of shops or outlets besides other facilities such as surau, rest areas, lobby and so on,” he said.

In September last year, Bernama reported BDB announced the joint venture company with Menteri Besar Kedah Incorporated, BDBMBI Langkawi Ventures Sdn Bhd would be developing an integrated commercial “premium outlet” encompassing business space, restaurants as well as recreational facilities in Langkawi. 

Che Had said the project in cooperation with Langkawi Development Authority is being developed in Padang Matsirat, located beside Langkawi International Airport.

Meanwhile, Che Had hoped the findings from the visit to Bernama would lead to forging closer cooperation and cordial ties between the company and Bernama.

“Through Bernama, we have the target to brand BDB with many programmes involving corporate social responsibility (CSR) and this is also necessary for us to express to the community about our social responsibility that we carried out as BDB’s close collaboration with the community, “ he said. – Bernama, June 29, 2022

Related News

Malaysia / 3h

Govt approves RM451m for projects in 66 opposition-held constituencies

Heritage / 5d

No development at Mount Erskine burial site: land is for cemetery-related purposes

Events / 2w

Penang launches its Smart City Blueprint 2040

Community / 4w

Paya Terubong landslide: Resident writes to 15 ADUN to seek ban on hillslope development

Opinion / 1mth

Thank you, Dr Siti Hasmah, for everything; You will be greatly missed

Malaysia / 2mth

Indian community will never be marginalised in development agenda – PM Anwar

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Business

NexG share surge puts spotlight on RM7.5b takeover proposal as SC examines trading

Business

MAG to add 10 Boeing Dreamliners in long-term fleet expansion drive

Business

Oil prices holds above US$80 as Hormuz attacks heighten supply concerns

Business

Oil retreat offers limited relief as ringgit weakens against firmer US dollar

Business

Three Malaysian firms placed on US trade blacklist over advanced technology diversion fears

Business

Pengerang needs to create wider economic value, not just store more oil, says expert

Business

Govt moves to block seven US-blacklisted entities from accessing local data centres