Malaysia

ECRL ahead of schedule, Dewan Negara told

Deputy transport minister says project’s overall construction progress nearly 1% ahead of time

Updated 5 years ago · Published on

ECRL ahead of schedule, Dewan Negara told
The Dewan Negara was told today that Section B of the East Coast Rail Link project, which links Dungun to Temerloh, is now over 2% ahead of schedule after resuming construction in July 2019. – ECRL pic, December 22, 2020

KUALA LUMPUR – Construction of the East Coast Rail Link (ECRL) project continues to advance beyond its original schedule, said Deputy Transport Minister Hasbi Habibollah.

Hasbi said as of November 30, the overall construction of the project achieved actual progress of 19.69% compared to the original schedule of 18.78%.

He said for Section A from Kota Baru to Dungun which includes the construction of six stations namely Kota Baru, Pasir Putih, Jerteh, Bandar Permaisuri, Kuala Terengganu and Dungun, physical work progress was 0.27% ahead of schedule.

Hasbi said for Section B from Dungun to Temerloh, construction which resumed in July last year, physical work progress has reached 7.54% compared to the schedule of 5.24%, covering earthworks and tunnel construction in Dungun, Paka and Kuantan.

“Preliminary works for the construction of tunnels in Gambang, Sri Jaya, Gedung Siam and Paya Pasir have begun,” he said, when winding up the debate on the 2021 Supply Bill at the Dewan Negara today.

As for Section C from Temerloh to Port Klang, he said the government was studying the best alignment to ensure ECRL gave maximum economic impact when completed and it would be announced when the study is completed.

On the status of the Sultan Ismail Petra Airport upgrade project in Kelantan, he said the project, which was implemented through a pre-qualifying open tender, was in the final stages of tender evaluation and was expected to be completed this month.

“The appointment of a contractor is scheduled for early next year and the project is expected to be completed in December 2023,” he said.

Hasbi said the airport is expected to accommodate four million passengers a year, an increase of 2.5 million passengers compared to the current capacity of 1.5 million passengers a year.

The total capacity of the landing aircraft will be increased from three to eight 4C code aircraft as well as from two ATR 72s to three ATR 72s. – Bernama, December 22, 2020

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Kuantan-Gombak rail journey to be cut to 90 minutes with ECRL launch

Malaysia

AKPS vows to help police uncover wider migrant-smuggling network after officer's arrest

Malaysia

Who will scam whom in the PAS-UMNO electoral alliance?

Malaysia

Dewan Rakyat to scrutinise online scam losses, recovery of stolen funds

Malaysia

Myanmar junta invitation faces Dewan Rakyat scrutiny as MPs raise 3R, AI concerns

Malaysia

Bloodstains, flesh fragments lead to discovery of man's body in Nibong Tebal

Malaysia

Court imposes gag order in case against AKPS chief Mohd Shuhaily

Malaysia

Sabah O&G contracts to local firms surge nearly ninefold to RM3b