Cable thefts derail timely completion of East Coast Rail Link

The ECRL is facing unexpected delays as thieves target critical signalling and communication infrastructure along the 665km alignment

Updated 1 year ago · Published on

Cable thefts derail timely completion of East Coast Rail Link
More than 1,200 metres of signalling cables and 81 outdoor transformer units have been reported stolen along the route, according to Malaysia Rail Link (MRL) Sdn Bhd (File pic) - June 23, 2025

THE East Coast Rail Link (ECRL) project, Malaysia’s major infrastructure initiative connecting the Klang Valley to the East Coast, is now facing a significant threat to its completion timeline due to a spate of cable and equipment thefts.

The Star cited today that over 1,200 metres of signalling cables and 81 outdoor transformer units have been reported stolen along the route, according to Malaysia Rail Link (MRL) Sdn Bhd. The incidents have raised concerns about project delays, particularly as the stolen components are custom-made and could take up to six months to replace.

“The thefts may delay the project delivery,” said MRL Chief Executive Officer Datuk Seri Darwis Abdul Razak. “We were very much looking forward to the testing and commissioning phase in June next year.”

The 665km rail line, which commenced construction in 2017 and has achieved 82.45% overall progress, is scheduled for completion by December 2026. Designed to carry both passengers and freight, it will support speeds of up to 160kph for passenger trains and 80kph for cargo services.

Since the installation of Communications, Information and Signalling (CIS) systems began at the KotaSAS Station in Pahang in March, at least seven locations across Pahang, Terengganu, and Kelantan have experienced thefts. These include Paya Besar, Cherating, Kuantan Port City, Chukai, Dungun, Kemasik, and Pasir Puteh.

Contractors discovered that in some areas, including near the KotaSAS Station, fibre optic cables were abandoned after being cut – likely due to their lack of value as scrap. However, the stolen signalling cables did contain metal, making them attractive to thieves.

Darwis said the project contractor, China Communications Construction Company (CCCC-ECRL), would bear the cost of the stolen materials, as the project has not yet been handed over to the government.

“That said, we as the project owner will also do our part to curb this problem. The ECRL project team is working closely with police to engage those in the scrap collection or recycling business,” he said.

He added that MRL will meet with state police chiefs and relevant ministers to discuss comprehensive asset protection measures. The project is also deploying more security patrols and installing CCTV at critical locations, though Darwis acknowledged the challenge of monitoring such an extensive alignment.

Plans are underway to fence off ground-level portions of the route to prevent future intrusions. “In the meantime, we appeal to the public to help us by quickly alerting authorities if they spot suspicious activities along the alignment,” Darwis said.

Yuslizar Daud, former head of the now-defunct Land Public Transport Commission’s Rail Division, noted that cable theft is a global issue. “It happens all over the world. In the United Kingdom, Network Rail lost almost £20 million (RM114.4 million) a year due to cable theft,” he said.

“Here, thieves are very smart and well-organised, with intricate networks. They are always 100 steps ahead of the operators,” he added, stressing the need for rail operators to collaborate and share intelligence.

CCCC-ECRL managing director Deng Bo described such thefts as a “serious crime” in China, warning that they endanger public safety by compromising rail operations.

Officials further warned that continued theft could lead to financial losses once the trains begin service in early 2027, as Malaysia is obliged to share half the operational costs, including any shortfalls. - June 23, 2025

Spotlight

Malaysia

Father and son escape death as 4WD swept 500m downstream after plunging into river

Malaysia

Shuhaily transferred from AKPS to IGP’s office

Malaysia

Anwar raises alarm over alleged Mossad expansion in southern Thailand

Malaysia

Woman loses RM208,700 after 15 transfers in fake job scam

Malaysia

Hannah: MACC has all details on Chinese Assembly Hall land lease

Malaysia

Penang DAP backs simultaneous state, general elections amid possibility of GE16 next August

By Ian McIntyre

Malaysia

Fadillah sees GE16 next year, urges Sarawak voters to give GPS stronger mandate

Malaysia

No missing RM225m research funds, says Higher Education Ministry

World

Netanyahu offers to step aside in proposed unity government led by rival Eisenkot

You may be interested

Malaysia

MySiren aims to close critical gap in emergency warnings

Malaysia

Police contain brief tension as anti-graft marchers encounter rival rally in Kuala Lumpur 

Malaysia

Nancy: A child needs more than academic success to thrive

Malaysia

Malaysia is not Colombia - Home Minister

Malaysia

Anwar raises alarm over alleged Mossad expansion in southern Thailand

Malaysia

Air Kelantan threatens SLAPP suit over complaints about water quality

Malaysia

Anwar urges Loke to resume duties as Transport Minister

Malaysia

No missing RM225m research funds, says Higher Education Ministry