Putra Heights gas pipe explosion: Repair, reconstruction work between 22 – 24 per cent, says MB

Repair work involves an allocation of RM40 million approved by the Cabinet, in addition to RM6 million to improve public infrastructure.

Updated 1 year ago · Published on

Putra Heights gas pipe explosion: Repair, reconstruction work between 22 – 24 per cent, says MB
The MB said the current progress level is between 22 and 24 percent. - July 8, 2025

THE repair and reconstruction work on houses destroyed and damaged due to the gas pipe explosion incident in Putra Heights last April is currently at a progress level of between 22 and 24 percent.

Selangor Menteri Besar, Datuk Seri Amirudin Shari, said the work involves 81 houses that were destroyed and 138 houses that were damaged in Kampung Kuala Sungai Baru and is expected to be completed this October.

“For the houses in Taman Putra Harmoni, the completion period is set for 24 months, which is until June 2027,” he said during the Selangor State Legislative Assembly (DUN) session today.

According to him, the implementation of the repair work involves an allocation of RM40 million that has been approved by the Cabinet, in addition to RM6 million to improve public infrastructure.

“Syarikat Perumahan Nasional Berhad (SPNB) has been tasked by the Ministry of Housing and Local Government to manage the repair and reconstruction of houses in Kampung Kuala Sungai Baru.

“All this work commenced since May 1,” he said.

The Cabinet has also decided that Sime Darby Property, as the original developer, be given the responsibility to rebuild and repair the affected houses in the area.

“So far, based on the Ecosystem Assessment Unit Test (UPE) for the reconstruction in Taman Putra Harmoni, three units will be rebuilt, while 46 units will be repaired and the remaining 46 units are currently in the final process of crack and structural testing.

“As for Kampung Kuala Sungai Baru, 17 units are involved; of that total, 11 units will be rebuilt while six more units will be repaired,” he said. – July 8, 2025

Related News

Malaysia / 1d

Negeri MB unwell, being treated in hospital

Malaysia / 4d

Ismail Lasim to remain as Negeri MB

Malaysia / 4d

Ismail meets Negeri Sembilan ruler amid leadership uncertainty

Malaysia / 5d

Puad challenges Ismail to explain circumstances surrounding resignation

Malaysia / 6d

Negeri Sembilan political crisis far from over?

Malaysia / 1w

Zahid: One name submitted for new Negeri MB

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Govt eyes up to 250,000 jobs from RM170bil carbon capture industry by 2050

Malaysia

Indonesia seizes RM229m in drugs from Malaysia-linked trafficking network

Malaysia

It wasn’t the Government that leaked Najib's conditional pardon documents - Anwar

Malaysia

AGC to defend royal institution, Constitution in Najib house arrest challenge

Malaysia

Former Najib aide, businessman ordered to pay preacher RM433,000 over RM400,000 conspiracy

Malaysia

Sabah O&G contracts to local firms surge nearly ninefold to RM3b

Malaysia

Hajiji: GRS has not decided on political cooperation for GE16

Malaysia

RAHMAH sales programme not long-term solution to cost-of-living pressures - Minister