Malaysia

UKM breached procurement procedures in RM66.64 million tenders, says Auditor-General

Audit report highlights serious irregularities in three high-value tenders awarded by Universiti Kebangsaan Malaysia, raising concerns over governance and compliance

Updated 1 year ago · Published on

UKM breached procurement procedures in RM66.64 million tenders, says Auditor-General
Audit also found that UKM had failed to include a representative from the Ministry of Finance (MoF) on its procurement committee. - July 21, 2025

UNIVERSITI Kebangsaan Malaysia (UKM) failed to comply with procurement regulations in the awarding of three out of seven tenders worth a combined RM66.64 million, according to the Auditor-General’s Report Series 2/2025 tabled in Parliament today.

The report revealed that UKM’s Tender Procurement Committee had selected companies that were not recommended by the Technical Evaluation Committee, the Financial Evaluation Committee, or the Pre-Tender Committee.

“There were serious irregularities and weaknesses in the tender procurement process and governance at UKM. Decisions by the Tender Procurement Committee were made collectively by its members,” the report stated.

It also cited an example where the Pre-Tender Committee endorsed a company that had failed the evaluation stage in a contract for upgrading and replacing 16 elevator units.

The Auditor-General further noted that the Vice-Chancellor, as Chair of the Procurement Committee, is responsible for ensuring proper governance and compliance in the university’s operations, in line with Subsection 12(3) of the UKM Constitution and the duty of care principle.

The audit also found that UKM had failed to include a representative from the Ministry of Finance (MoF) on its procurement committee. Meanwhile, the representative from the Ministry of Higher Education (MoHE), though appointed, was absent from key meetings related to the three tenders in question.

Among the breaches identified was the selection of a supplier for a Linear Accelerator (LINAC) that did not meet compatibility specifications with the existing ARIA system, and the shortlisting of a food catering company that had failed the technical evaluation stage.

The report also flagged the awarding of a lift replacement contract to a company classified as a “sick project” contractor, bypassing the recommendations of all three evaluation committees. This decision, it said, led to the selection of a company incapable of delivering the contract within the stipulated timeline.

To address these failings, the National Audit Department has recommended that UKM revise its procurement guidelines to align with Treasury Circulars and ensure close monitoring of equipment delivery and lift replacement work at Hospital Canselor Tuanku Muhriz (HCTM) to ensure deadlines are met.

“In addition, disciplinary action is also recommended against the officers and committee members involved, subject to the findings of the MoHE’s Internal Investigation Committee,” the report stated.- July 21, 2025

Spotlight

Malaysia

Father and son escape death as 4WD swept 500m downstream after plunging into river

Malaysia

Shuhaily transferred from AKPS to IGP’s office

Malaysia

Anwar raises alarm over alleged Mossad expansion in southern Thailand

Malaysia

Woman loses RM208,700 after 15 transfers in fake job scam

Malaysia

Hannah: MACC has all details on Chinese Assembly Hall land lease

Malaysia

Penang DAP backs simultaneous state, general elections amid possibility of GE16 next August

By Ian McIntyre

Malaysia

Fadillah sees GE16 next year, urges Sarawak voters to give GPS stronger mandate

Malaysia

No missing RM225m research funds, says Higher Education Ministry

World

Netanyahu offers to step aside in proposed unity government led by rival Eisenkot

You may be interested

Malaysia

‘I am not RMAF’s enemy. I just want to combat traitors’ - PMX

By Ian McIntyre

Malaysia

Police contain brief tension as anti-graft marchers encounter rival rally in Kuala Lumpur 

Malaysia

Anwar raises alarm over alleged Mossad expansion in southern Thailand

Malaysia

Sarawak PRN: GPS wins 29 seats unopposed, just 13 short of simple majority

Malaysia

Woman loses RM208,700 after 15 transfers in fake job scam

Malaysia

Air Kelantan threatens SLAPP suit over complaints about water quality

Malaysia

Malaysians set to receive nationwide emergency alerts in MySiren test tomorrow

Malaysia

WAO sees rise in domestic violence cases, warns of growing digital abuse