One year on, Putra Heights blast victims await return home amid slow rebuilding

Displaced families continue to endure cramped living conditions as repairs progress unevenly and residents press for stronger safety guarantees before gas pipeline resumes operations

Updated 7 months ago · Published on

One year on, Putra Heights blast victims await return home amid slow rebuilding
Residents sought compensation for losses not covered by insurance, engaging with Petronas Gas Bhd to address outstanding claims - April 1, 2026

A YEAR after the gas pipeline explosion in Putra Heights forced mass evacuations, many residents remain displaced, grappling with prolonged uncertainty as rebuilding works continue and questions over safety persist.

The blast on April 1 last year devastated parts of Taman Putra Harmoni, leaving families such as that of Loh Weng Fei and his wife Katie Phan still living in cramped temporary accommodation.

The couple and their two children have been sharing a single room at a relative’s home since the incident, prompting one of their children to move into a school hostel due to lack of space.

“My daughter goes to school six days a week, so I only get to see her once a week. I miss her so much,” Phan told The Star.

Residents say they have been trying to adjust to the disruption while waiting for repairs to be completed.

“Now, we are just hoping for repairs to be finished so that we can move back in,” said another resident, Yap Geok Wah.

A visit to Jalan Putra Harmoni 1/3, the site of the explosion, shows reconstruction progressing at varying speeds, with some homes nearing completion while others remain under repair.

According to Francis Koh, the initial months after the disaster were especially difficult for affected households.

“The Housing and Local Government Ministry had introduced the repair-and rebuild programme for those whose homes were destroyed.

“Letters of acceptance were prepared for those who agreed to the programme and by September 2025 works started.

“At the Amber section of the neighbourhood, we have 22 houses under this programme.

“They are mostly located along Jalan Putra Harmoni 1/3C and Jalan Putra Harmoni 1/3D.

“Of the 22, repairs for three were completed at the end of last December.

“Mine was one of the three,” he added.

Koh said he returned to his home in late January alongside two neighbours, but many others are still waiting.

“During our engagement with the ministry, the developer, main contractor and Subang Jaya City Council just before Hari Raya, we were told that residents could be looking at August as a possible date for repair completion,” he said.

Residents have also raised technical concerns during the rebuilding process, particularly regarding structural damage caused by the heat of the explosion.

“At first, only broken roof tiles were scheduled to be replaced but residents pointed out that the intense heat from the blast had compromised their durability.

“After our appeals, it was finally agreed that all the roof tiles would be replaced and the wooden roof trusses would be repaired,” he said.

Another point of contention has been the scope of restoration, with authorities initially committing to return homes only to their original condition.

“After 15 years, some of the houses had already undergone approved extensions.

“Yet repairs would only be carried out up to the houses’ original condition before the extensions,” Koh added.

Residents have also sought compensation for losses not covered by insurance, engaging with Petronas Gas Bhd to address outstanding claims.

“After a series of town halls, PGB came back to us with a third-party insurance programme called Laman, which was announced last September.

“Now the more important thing is to ensure there are safety mechanisms in place when the gas pipeline is restored.

“We are asking PGB to put in more alerts that are visible, like alarms or lights when something happens such as pressure changes or when there is any leakage.

“PGB has also set up a WhatsApp group with the residents so that there is direct communication between both parties.

“In preparation for any future emergencies, PGB, the Fire and Rescue Department and Subang Jaya City Council will be doing a safety route review.

“A fire drill will also be conducted,” he said.

Local assemblyman S. Preakas said he remained committed to ensuring residents received appropriate compensation, as recovery efforts continue a year after the disaster. - April 1, 2026

Spotlight

Malaysia

No nation will become poor by helping the poor – Anwar

Malaysia

Negeri Sembilan PH lauds Tuanku Muhriz’s wisdom in handling political crisis

Malaysia

I am not disappointed at not being appointed Menteri Besar – Jalaluddin

Malaysia

DAP demands equal enforcement after three leaders summoned for questioning

Malaysia

Deaf man’s alleged knife attack on disable girlfriend: Court defers charge for sign language interpreter

Malaysia

Negeri Sembilan Exco to meet twice weekly to clear two-month backlog

Malaysia

‘Do not repeat past mistakes,’ Tuanku Muhriz warns new Negeri Sembilan Exco

People

Penang Exco stuck in traffic resorts to video call to greet guests at event

By Ian McIntyre

You may be interested

Malaysia

Negeri Sembilan PH lauds Tuanku Muhriz’s wisdom in handling political crisis

Malaysia

Negeri Sembilan Exco to meet twice weekly to clear two-month backlog

Malaysia

Malaysia ranks second in global confidence over country’s direction

By Alfian Z.M. Tahir

Malaysia

FMM rejects US overcapacity claims, warns blanket tariffs could hurt Malaysian manufacturers

Malaysia

Tony Pua tells UMNO, PAS to understand law over Najib pardon minutes controversy

Malaysia

Kasikornbank’s “45 is the new 60”: An early warning of AI’s coming job squeeze

Malaysia

Zulkifli warns radio station over viral video parodying Islamic prayers

Malaysia

MACC denies selective investigations, says RM2.1b overspending probe ongoing