Penang: Upgrading of bypass delayed due to financial setback

Once ready, the bypass, which originates from the highly dense Air Itam township, will reduce travel time to the Penang Bridge from 40 minutes to around ten minutes.

Updated 5 months ago · Published on

Penang: Upgrading of bypass delayed due to financial setback
Chow also dismissed claims that the Covid-19 remained a factor in the delays. - May 26, 2026

by Ian McIntyre

UPGRADING of the 6km bypass between Air Itam and the Tun Dr Lim Chong Eu Expressway in Penang has hit a snag after the developer encountered financial issues.

With rising living costs and disruptions to the supply chain due to the Middle East conflict, Chief Minister Chow Kon Yeow confirmed that the developer, Consortium Zenith Construction Sdn Bhd, has slowed its construction phase due to land acquisition and internal financial constraints.

The project is still scheduled to be ready by the end of this year, at the latest, by April 2027.

Once ready, the bypass, which originates from the highly dense Air Itam township, will reduce travel time to the Penang Bridge from 40 minutes to around ten minutes.

Chow was responding to criticism that the roadworks would take nearly 14 years from their initial award to completion, compared to the previous estimate of six years.

"The contract was awarded in 2020. How can it be 14 years?" he told journalists.

The 6 km elevated bypass, costing RM851 million, was initially slated for completion in 2025 before being extended due to the various issues encountered by Zenith.

"There are delays, but it has not reached the final deadline yet, which is April 2027," Chow replied to pressing queries.

"I think it is due to financial issues involving the concession company," he added.

Chow also dismissed claims that the Covid-19 remained a factor in the delays.

He earlier also said that the state has yet to make any decision on the proposed RM1 billion Jelutong landfill rehabilitation and reclamation project pending presentation from Penang Development Corporation (PDC).

“Tomorrow is a holiday, so PDC will present to the state exco next week,” he told reporters after launching a “Oh Malaysiaku” music video at 1st Avenue Mall here.

The event was organised by the developer, Ideal Property Group.

The contractor of the proposed project - PLB Engineering Sdn Bhd, was scheduled to present working papers on the project to apply for an extension of time to meet the requirements of the approving agency, the Department of Environment (DOE).

The project’s Environmental Impact Assessment (EIA) application was rejected by the DOE for the fifth time in March this year.

It was reported that PLB has resubmitted another application after updating the requirements in accordance with the conditions set by the DoE.

PDC signed a deal with PLB Engineering Bhd to rehabilitate and develop the Jelutong landfill at RM1 billion back in 2020.

The project included the reclamation of 30ha of land off Karpal Singh Drive, which has received backlash from an action group of residents living in the adjacent Karpal Singh Drive neighbourhood.

Protect Karpal Singh Drive Action Committee members have repeatedly called for the project to be cancelled due to environmental concerns, especially its proximity to the Middle Bank Marine Sanctuary.

The sanctuary spreads around 10 square kilometres in the waters of the South Channel between Penang Island and the mainland.

It is home to a seagrass bed, and a study has revealed that a total of 429 species of seagrass, trees, vegetation, fish, birds, marine mammals, turtles, molluscs, arthropods and echinoderms were found there. - May 26, 2026.

Related News

Stage / 1d

Dancers thrill audience with their enchanting ballet performance

Malaysia / 2d

Penang must appreciate what Anthony Loke has done - Guan Eng

Books / 3d

Book on the life and legacy of Tun Tan Cheng Lock launched

Malaysia / 1w

1MDB’s burden will outlive the generation that witnessed its rise

Off beat / 1w

Penang moves to strengthen position as green manufacturing hub

Events / 1w

Annie Tan looks to keep traditional Asian flavours relevant through modern dining

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

Türkiye's four million refugee burden behind rejection of Malaysia's Rohingya request

Malaysia

MOF warns public of fake accounts impersonating deputy finance minister, Treasury chief

Malaysia

Filipino man jailed 10 years for sexually assaulting 10-year-old girl in Lahad Datu

Malaysia

Johor accounts for 17.1% of Malaysia's agricultural GDP, leads nationwide

Malaysia

It wasn’t the Government that leaked Najib's conditional pardon documents - Anwar

Malaysia

MPs urged to debate merits of reinstating GST as against SST, says Liew Chin Tong

Malaysia

Fourteen diaries preserve 100-year-old woman's first-hand memories of Japanese occupation