Penang’s Air Itam-Tun Dr Lim Chong Eu bypass nearing completion

The infrastructure is one of several key projects, which are designed to alleviate the worsening congestion on the island.

Updated 2 months ago · Published on

Penang’s Air Itam-Tun Dr Lim Chong Eu bypass nearing completion
The project's landbank cost is RM695.977 million, of which the consortium is seeking the same figure through land swaps, said Zairil. - September 7, 2026

by Ian McIntyre

THE Air Itam-Tun Dr Lim Chong Eu bypass edges closer to completion, with Penang disclosing that 92.46 per cent of the construction phase is done.

As of last month, there is a 92.46 percent completion rate, although the financial payout to the contractor and project delivery partner is only 81.69 per cent finalised, said state executive councillor Zairil Khir Johari.

"The project is not paid through cash sales, but through land swaps, so we need to ready the necessary land to be accorded to the delivery partner - Consortium Zenith Construction Sdn Bhd," said Zairil in a statement.

The project's landbank cost is RM695.977 million, of which the consortium is seeking the same figure through land swaps, said Zairil.

For now, the state has surrendered a landbank total of 11,6183 acres or RM427.657 million with the remainder of RM225.768 million as the shortfall.

The consortium has asked Penang to monetise land sales to help it with its cash flow needs so the project can be fully completed by April next year, he said.

"Penang has agreed to conduct a public auction of a land site as part of the consortium's claim. It is a prime land location of six acres at PT858 (Plot 7A) under Section 2 of the Tanjung Pinang Township (off Gurney Drive)."

Zairil revealed that the state will auction the plot from Wednesday at 11 am.

The land is located next to Gurney Bay and the (reclaimed) Andaman Island, with the reserve prices going at RM313.632 million as starters.

The sale proceeds from the land would be shared between the state government and the consortium.

Those who need to participate in the bidding can do so by liaising at the state office on Level 51, in the Komtar administrative complex.

The infrastructure is one of several key projects, which are designed to alleviate the worsening congestion on the island.

It will be the first elevated highway to be completed, with two more - the Tanjung Bungah - Teluk Bahang link highway and the Gurney Drive - Tun Dr Lim Chong Eu Expressway as the other two bypasses proposed.

Besides that, Penang is also witnessing an unprecedented range of infrastructure projects to be completed - there is ongoing construction for the Mutiara Light Railway Transit project, the Silicon Island reclamation and in Prai, the upgrading of the Juru - Sungai Dua highway stretch in the North - South Expressway.

The projects mean that Penang will witness many construction projects taking place along the public roads and social amenities in the state. - September 7, 2026.

Related News

Stage / 1d

Dancers thrill audience with their enchanting ballet performance

Malaysia / 2d

Penang must appreciate what Anthony Loke has done - Guan Eng

Books / 3d

Book on the life and legacy of Tun Tan Cheng Lock launched

Malaysia / 4d

Ismail vows to resign if state government breaches undertaking to Tuanku Muhriz

Malaysia / 5d

Negeri MB expected to seek audience with Tuanku Muhriz soon?

Off beat / 1w

Penang moves to strengthen position as green manufacturing hub

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Companies must pay higher wages to translate economic growth into better livelihoods, says Liew

Malaysia

Johor accounts for 17.1% of Malaysia's agricultural GDP, leads nationwide

Malaysia

Malaysia's first Global Minimum Tax revenue not expected until second half of 2027

Malaysia

AKPS vows to help police uncover wider migrant-smuggling network after officer's arrest

Malaysia

Singaporean fugitive wanted for corruption arrested in Johor after four years on the run

Malaysia

Govt eyes up to 250,000 jobs from RM170bil carbon capture industry by 2050

Malaysia

RAHMAH sales programme not long-term solution to cost-of-living pressures - Minister

Malaysia

MOF warns public of fake accounts impersonating deputy finance minister, Treasury chief