LCS delays revive questions over warnings raised by former navy chief

Several supplementary contracts linked to the fleet’s full readiness are only expected to be completed by December 2035, about five years after the main contract ends on April 25, 2030.

Updated 1 month ago · Published on

LCS delays revive questions over warnings raised by former navy chief
The latest audit shows that issues surrounding the LCS programme extend beyond the delays that marked its earlier stages. - October 7, 2026

THE latest audit findings on the littoral combat ship (LCS) programme have renewed scrutiny of warnings raised by former Navy chief Admiral Tan Sri Abdul Aziz Jaafar during the project’s early stages.

The Auditor-General’s Report 2/2026 found that the overall programme was 7.55% behind schedule as at June 25, with delays ranging from 30 to 108 days.

The first LCS, initially scheduled for physical handover on Aug 26, 2026, is now targeted for delivery on Dec 26.

However, the National Audit Department said the ship would not be fully operational if handed over on that date, as training and weapons systems would not yet be complete.

Several supplementary contracts linked to the fleet’s full readiness are only expected to be completed by December 2035, about five years after the main contract ends on April 25, 2030.

The delays could also affect the delivery schedule for LCS 2 to LCS 5, raising questions over when the fleet will achieve the capabilities stipulated under the programme.

The development has brought renewed attention to concerns Abdul Aziz raised over the procurement process.

Records of Public Accounts Committee (PAC) proceedings show that he had written to several senior government officials, including then prime minister Datuk Seri Najib Razak, then defence minister Datuk Seri Ahmad Zahid Hamidi, the Chief Secretary to the Government and the Treasury secretary-general.

Abdul Aziz raised concerns about the Royal Malaysian Navy's (TLDM) position as the end user, saying its views were not given due consideration during the procurement process.

During PAC proceedings, he described the situation as “something is gravely wrong” after the navy’s views were not taken into account in the implementation of the project.

The PAC’s 2022 report found that the government had paid RM6.083 billion for the LCS programme, although none of the ships had been completed according to the original schedule at the time.

The committee also found that the government’s due diligence on Boustead Naval Shipyard (BNS) had failed to identify the company’s financial problems before advance payments of up to RM1.36 billion were made.

The latest audit shows that issues surrounding the LCS programme extend beyond the delays that marked its earlier stages.

Several supplementary contracts remain unfinished as the government works towards the delivery of the first ship.

One is the RM535.37 million Integrated Logistics Support and Trial Aids (ILS-TA) contract.

The National Audit Department said its contract documents had not been formally finalised as at June 25, despite two progress payments totalling RM100 million having been made.

The department recommended that the Defence Ministry draw up a realistic recovery plan and strengthen monitoring by assigning officers to address critical issues and setting deadlines for their resolution.

The LCS programme has now moved well beyond its original delivery timetable, with the latest audit raising fresh concerns over both the completion of supporting contracts and the operational readiness of the ships.

For the government, the immediate task is to ensure that the first vessel is not only handed over, but can eventually operate with the systems, training and support required under the programme. – October 7, 2026

Related News

Malaysia / 1d

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Malaysia / 4d

'I'm bored with the repeated criticism from Umno' - Tony Pua

Malaysia / 5d

Najib has been given a second chance. But where is the accountability to Malaysians?

Malaysia / 6d

Umno seeks clarification on declassification of Najib's pardon board minutes

Malaysia / 6d

Najib’s house arrest: Govt, AG, Hannah opposed conditional pardon, minutes show

Malaysia / 1w

Padang Rengas dispute exposes challenge facing possible BN-PN pact

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Mother returns to SPM examination hall after 20 years to stand alongside autistic son

Malaysia

Companies must pay higher wages to translate economic growth into better livelihoods, says Liew

Malaysia

Filipino man jailed 10 years for sexually assaulting 10-year-old girl in Lahad Datu

Malaysia

AKPS vows to help police uncover wider migrant-smuggling network after officer's arrest

Malaysia

Four 1MDB-linked paintings to be displayed publicly, free of charge

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

Malaysia

Fourteen diaries preserve 100-year-old woman's first-hand memories of Japanese occupation

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya