PAC to probe Sabah Pan Borneo Highway delays despite RM10.5b spent

Only four of 35 work packages have been completed despite RM10.547 billion being spent and the completion deadline pushed back to 2030

Updated 1 month ago · Published on

PAC to probe Sabah Pan Borneo Highway delays despite RM10.5b spent
The Parliament’s Public Accounts Committee will investigate financial management, governance and construction delays in the Sabah Pan Borneo Highway Phase 1 project - October 19, 2026

THE Public Accounts Committee (PAC) will investigate how RM10.547 billion was spent on the Sabah Pan Borneo Highway Phase 1 project, with only four of its 35 work packages completed despite the project being scheduled for completion in 2021.

PAC chairman Datuk Mas Ermieyati Samsudin said the inquiry would examine project management, financial governance and physical progress, including why existing monitoring mechanisms had failed to prevent prolonged delays.

She said the committee would scrutinise how project payments were approved when construction progress on the ground did not correspond with the amount of public funds spent.

PAC will call witnesses from the Works Ministry, the Public Works Department (JKR), including JKR Sabah, as well as other relevant agencies and parties to give evidence.

“PAC will not hesitate to refer its findings to the Malaysian Anti-Corruption Commission (MACC) and the Royal Malaysia Police for further investigation if the proceedings uncover any indications of misconduct, corruption or abuse of power,” she told a press conference at Parliament today.

Mas Ermieyati said the inquiry followed findings in the Auditor-General’s Report Series 2/2026, which highlighted weaknesses in public fund management, non-compliance with financial rules, excessive expenditure linked to poor project management and significant delays.

The Sabah Pan Borneo Highway Phase 1 project comprises 35 work packages covering 706km and was originally scheduled to be completed within 69 months, with the deadline set for the end of 2021.

However, only four packages, or 11.4%, have been completed, while the remaining 31 packages, valued at RM16.319 billion, are still under implementation.

Of those remaining packages, nine have been classified as sick projects and 13 are behind schedule, while nine are ahead of schedule.

Mas Ermieyati said RM10.547 billion, equivalent to 94.6% of the RM11.153 billion allocated, had been spent between 2016 and March 31 this year despite the project’s physical progress lagging significantly.

The completion deadline has since been extended to 2030, while the overall contract cost has risen to RM18.394 billion from RM17.910 billion.

She said PAC was committed to conducting an independent, transparent and comprehensive inquiry to ensure public funds were spent prudently, responsibly and in accordance with regulations. - October 19, 2026

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

404,848 Malaysians hit with overseas travel bans since 2024, says Immigration chief

Malaysia

Sabah O&G contracts to local firms surge nearly ninefold to RM3b

Malaysia

Türkiye's four million refugee burden behind rejection of Malaysia's Rohingya request

Malaysia

AKPS vows to help police uncover wider migrant-smuggling network after officer's arrest

Malaysia

Hannah: KLSCAH land premium row would not arise if minister was not from DAP

Malaysia

Johor accounts for 17.1% of Malaysia's agricultural GDP, leads nationwide

Malaysia

Federal Government, Sabah and Sarawak continue talks on new special grant formula

Malaysia

PAC flags eight-month delay in UKM conflict-of-interest probe