Penang aims to settle undersea tunnel feasibility study by Q2 2021

Once state exco, committee clears it, detailed design of mega project will start, says Zairil Khir Johari

Updated 5 years ago · Published on

Penang aims to settle undersea tunnel feasibility study by Q2 2021
A feasibility study for Penang's undersea tunnel project started in December 2014 and was supposed to be completed in 2016 but was delayed due to various reasons. – MATHIS SARAWANAN/The Vibes pic, January 21, 2021

by Sofia Nasir

GEORGE TOWN – The Penang government wants all matters related to the approval of a feasibility study for the controversial RM6.3 billion undersea tunnel project to be sorted out before the second quarter of this year.

State Transport and Infrastructure Committee chairman Zairil Khir Johari said the project delivery partner for the tunnel and three highways projects, Consortium Zenith Construction (CZC), had completed the study last month.

However, the presentation of the study to the state executive council and technical committee has been postponed due to the implementation of movement control order (MCO).

“It should be presented to the technical committee first, but because of the MCO, there is a slight delay,” he said.

"I hope all matters related to this feasibility study can be completed before the second quarter of 2021," he told The Vibes.

"After completing the feasibility study, we will continue with the detailed design of the undersea tunnel."

The feasibility study started in December 2014 and was supposed to be completed in 2016 but had been delayed due to various reasons.

CZC presented the draft feasibility report in September 2019 and it was amended with improvements based on reviews by various agencies.

In July last year, the Malaysian Anti-Corruption Commission (MACC) reopened its investigation into the undersea tunnel project in Penang, following new evidence linked to the matter.

The mega project has courted various objections, particularly involving the RM305 million feasibility study and delay of its original scheduling.

Based on the original plan, the project includes four main components, namely three main roads along a 30km stretch and the undersea tunnel between Gurney Drive on the island and Bagan Ajam on the mainland. – The Vibes, January 21, 2021

Related News

Stage / 1d

Dancers thrill audience with their enchanting ballet performance

Malaysia / 2d

Penang must appreciate what Anthony Loke has done - Guan Eng

Books / 3d

Book on the life and legacy of Tun Tan Cheng Lock launched

Off beat / 1w

Penang moves to strengthen position as green manufacturing hub

Events / 1w

Annie Tan looks to keep traditional Asian flavours relevant through modern dining

Community / 1w

Penang looks towards AI for greater sustainability

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Malaysia

Singaporean fugitive wanted for corruption arrested in Johor after four years on the run

Malaysia

PH still has opportunity to win over young Malay voters, says Ilham Centre

Malaysia

Companies must pay higher wages to translate economic growth into better livelihoods, says Liew

Malaysia

Türkiye's four million refugee burden behind rejection of Malaysia's Rohingya request

Malaysia

Former Najib aide, businessman ordered to pay preacher RM433,000 over RM400,000 conspiracy

Malaysia

Sabah O&G contracts to local firms surge nearly ninefold to RM3b

Malaysia

Indonesia seizes RM229m in drugs from Malaysia-linked trafficking network