NGO questions Penang’s ‘deliberate’ move to proceed with PSR

EIA report, court case still pending, so why is project slated to begin end-March?

Updated 5 years ago · Published on

NGO questions Penang’s ‘deliberate’ move to proceed with PSR
A master plan design of the Penang South Islands, which involves the development of three man-made islands under the Penang South Reclamation project. – Penangpropertytalk pic, February 10, 2021

by Rachel Yeoh

GEORGE TOWN – A non-governmental organisation (NGO) is questioning the Penang government’s decision to go ahead with the Penang South Reclamation (PSR) project despite unresolved environmental impact assessment (EIA) issues.

Penang Malay Thinkers chairman Datuk Muhamad Farid Saad in a statement said this includes an injunction filed by the Penang Fishermen’s Association, which has yet to be heard by the state Environment Department’s (DoE) board of appeal.

He said the case will be heard on March 23, 25 and 26.

“They (association members) are waiting for the outcome of the case before resuming discussions with the Penang government.

“The state government knows about this, but deliberately made a statement to continue the project at the end of March or April.”

The association adheres to a statement made by Environment and Water Minister Datuk Seri Tuan Ibrahim Tuan Man at the last sitting of the Dewan Rakyat in 2020 that the project cannot proceed until and unless its EIA-related issues are resolved.

Penang Infrastructure Corporation chief executive Datuk Seri Farizan Darus said he has submitted an environmental management plan report to the DoE, but has yet to receive any decision on the matter.

“There are 72 conditions that have been given by the department via a letter issued on June 25, 2019.

“If the minister’s statement in the Dewan Rakyat is a requirement for compliance with the conditions for project approval, the project cannot be allowed to start before approval is obtained.”

Penang Malay Thinkers chairman Datuk Muhamad Farid Saad has labelled as immoral the Penang government’s move to take into account part-time and unlicensed fishermen’s views in making a decision on the Penang South Reclamation project. – Muhamad Farid Saad Facebook pic, February 10, 2021
Penang Malay Thinkers chairman Datuk Muhamad Farid Saad has labelled as immoral the Penang government’s move to take into account part-time and unlicensed fishermen’s views in making a decision on the Penang South Reclamation project. – Muhamad Farid Saad Facebook pic, February 10, 2021

Farid questioned the Penang government’s discussions with local fishermen in the absence of the association, which is a legitimate institution that represents fishermen.

“The action by the state government to take into account the views of part-time and unlicensed fishermen in making a decision is an immoral act.”

He urged the federal and Perak governments to look into the matter, as it not only involves 4,995 Penang fisherfolk, but also 6,080 fishermen in Kerian, Larut, Matang and Manjung districts in Perak.

“Promises of jobs by SRS Consortium Sdn Bhd to locals, especially fishermen, are just sweet words that are never made official.

“Fishermen can still go to sea, but they need a bigger boat with a larger capacity as they now have to go further, and this incurs cost.

“Even though SRS says that fishermen still have the vast sea, they know that the reclaimed land is the main catchment area.”

Farid said a RM20,000 compensation is unreasonable as it is similar to the rate paid to Tg Tokong fishermen during the Seri Tg Pinang sea reclamation years ago.

“Only the developer knows the actual composition of the development on the PSR project, which includes three man-made islands.

“Developers may calculate their profits, but forget to calculate profits of the community, directly and indirectly.”

Other NGOs opposing the project include the Consumers’ Association of Penang, Friends of the Earth Malaysia, Penang Forum and Penang Heritage Trust.

They raised issues surrounding the impact of the project on, among others, the environment and marine ecosystems, population psychology, aesthetic values of historic areas, community identity and traditional village heritage.

They also highlighted compensation issues and the future of fishermen.

The PSR project will be executed in phases starting end-March, beginning with the reclamation of Island A. – The Vibes, February 10, 2021

Related News

Stage / 1d

Dancers thrill audience with their enchanting ballet performance

Malaysia / 2d

Penang must appreciate what Anthony Loke has done - Guan Eng

Books / 3d

Book on the life and legacy of Tun Tan Cheng Lock launched

Off beat / 1w

Penang moves to strengthen position as green manufacturing hub

Events / 1w

Annie Tan looks to keep traditional Asian flavours relevant through modern dining

Community / 1w

Penang looks towards AI for greater sustainability

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Sabah O&G contracts to local firms surge nearly ninefold to RM3b

Malaysia

Malaysia's first Global Minimum Tax revenue not expected until second half of 2027

Malaysia

Federal Government, Sabah and Sarawak continue talks on new special grant formula

Malaysia

Tuanku Muhriz supporters demand probe into alleged impersonation at royal event

By Alfian Z.M. Tahir

Malaysia

Amir Hamzah keeps focus on Finance Ministry mandate as Dec 11 term expiry looms

Malaysia

Cost of living remains biggest test for Anwar after four years in power

Malaysia

Hajiji: GRS has not decided on political cooperation for GE16

Malaysia

Kuantan-Gombak rail journey to be cut to 90 minutes with ECRL launch