Bukit Kukus project delayed again, this time due to fault lines

Highway opening pushed back 5 months to October after inspection authority discovers fissures spanning 2km along route

Updated 5 years ago · Published on

Bukit Kukus project delayed again, this time due to fault lines
The Bukit Kukus Highway was found to cut through several fault lines, one of which is the Sg Air Putih-Sg Dondang fissure. – RACHEL YEOH/The Vibes pic, April 11, 2021

by Rachel Yeoh

GEORGE TOWN – The opening of the Bukit Kukus Highway will be delayed by another five months to October this year instead of May, partly waylaid by the movement control order as well as the discovery of fault lines at a hill the expressway cuts through.

Soil expert and scientist Kam Suan Pheng said the fault lines, which span a 2km stretch of the Bukit Kukus Highway, is a warning of things to come, such as the construction of the Pan Island Link 1 (PIL1) under the Penang Transport Master Plan.

The Bukit Kukus Highway is located at the southern end (location roughly highlighted in red) of a fault line that runs up north. It is called the Sg Air Putih-Sg Dondang fault line (light blue dotted line). – File pic, April 11, 2021
The Bukit Kukus Highway is located at the southern end (location roughly highlighted in red) of a fault line that runs up north. It is called the Sg Air Putih-Sg Dondang fault line (light blue dotted line). – File pic, April 11, 2021

According to the PIL1 Environment Impact Assessment (EIA) report, the highway, represented by the green line on the map, intersects with more than one fault line.

“Fault lines are fissures in the rock formed when molten magma from the hot interior of the earth solidifies to form rock. Geologically, Penang island is essentially made of granitic rock.

“Some fault lines are shallow; others are deep into the bedrock and require geotechnical investigations deep into the bedrock to be detected.

“In the Bukit Kukus Highway’s case, either the geotechnical investigations were not done, or were done but not deeply enough,” she said.

She added if the original alignment hits a fault line, then there needs to be a realignment, which is a costly affair and will inflict environmental damage.

She said fault lines constitute a weakness in the rock structure, which makes it possible for groundwater to enter the fault line and further weaken the rock.

State exco for infrastructure and transport Zairil Khir Johari assures there is no need to worry, as this is why Environment Impact Assessment studies are done: to ensure the project route is safe and workable. – RACHEL YEOH/The Vibes pic, April 11, 2021
State exco for infrastructure and transport Zairil Khir Johari assures there is no need to worry, as this is why Environment Impact Assessment studies are done: to ensure the project route is safe and workable. – RACHEL YEOH/The Vibes pic, April 11, 2021

“Imagine if the fault lines had already started cutting the hill slopes, and if workers had already began digging underground for the tunnel and hit a fault line. They would have had to realign the road or tunnel, leading to more cutting or digging and abandoning what has already been (worked on).

“Or, at best, they may have to utilise some engineering remedy, which will hike up the construction cost at the expense of taxpayers’ money, which is precisely what’s happening now with the Bukit Kukus Highway.

“This will add to delays and increased costs, while inconveniencing road users as the construction work drags on.”

State exco for infrastructure and transport Zairil Khir Johari assured there is no need to worry as all steps needed to ensure safety to future users and the environment have already been taken.

This delay is justified and unavoidable.

“That’s why we have EIA studies, geotechnical consultants, geologists and others.

“Obviously, steps will be taken to mitigate the situation during the designing stage, but sometimes things happen beyond our control. What we can do is to minimise the risk by taking all possible steps,” he told The Vibes.

“There is no way to find these fault lines other than what we did, which is to check after cutting through the hill at a certain gradient.

“This is what we did – take precautions.

“Hence, this delay is justified and unavoidable.” – The Vibes, April 11, 2021

Related News

Malaysia / 7mth

163 unauthorised non-Muslim places of worship identified on public land in KL – Hannah Yeoh

Malaysia / 9mth

Anwar reminds all parties to stick to the laws when preaching, building houses of worship

Events / 1y

PM to launch two major projects in Penang over the weekend

Malaysia / 1y

Penangites told to brace for ‘higher congestion rate’ as LRT project begins

Malaysia / 1y

Guan Eng urges MOF to suspend SST on construction sales, commercial property rentals

Culture / 1y

Penang Hospital undergoing major upgrades to provide better services

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Kuantan-Gombak rail journey to be cut to 90 minutes with ECRL launch

Malaysia

88 days on, families of missing Nepal disaster victims still await DNA results, death certificates

Malaysia

MOF warns public of fake accounts impersonating deputy finance minister, Treasury chief

Malaysia

PH still has opportunity to win over young Malay voters, says Ilham Centre

Malaysia

It wasn’t the Government that leaked Najib's conditional pardon documents - Anwar

Malaysia

MPs urged to debate merits of reinstating GST as against SST, says Liew Chin Tong

Malaysia

Malaysia's first Global Minimum Tax revenue not expected until second half of 2027

Malaysia

Elderly man’s rampage leaves police officer injured in Sungai Besar