Ampang LRT disruption to continue until Sept: Loke

Two months needed for strengthening work, five for comprehensive repairs, says minister

Updated 3 years ago · Published on

Ampang LRT disruption to continue until Sept: Loke
Services on the route between the Masjid Jamek and Bandaraya LRT stations have been discontinued temporarily due to structural damage to the flyover in the area, believed to be the result of construction work adjacent to the area concerned. – ABDUL RAZAK LATIF/The Vibes file pic, February 22, 2023

KUALA LUMPUR – Ampang LRT users will have to put up with the disruption between its Bandaraya and Masjid Jamek stations until September as the structural repairs will take up to seven months to complete.

Transport Minister Anthony Loke said two months are needed for work to strengthen the structure, while five months are for comprehensive repair work.

“This will take time as investigations showed that the structural damage poses a very serious safety risk,” said Loke in a press conference in Parliament today.

He added that Prasarana Malaysia Bhd will implement mitigating steps to avoid such disruptions in the future, and make sure users are comfortable at all times. 

“When the Putrajaya MRT line opens in mid-March, commuters on the Ampang and Sri Petaling LRT line can use interchange stations such as Chan Sow Lin, Titiwangsa, and Sg Besi as alternatives.”

Previously, Ampang LRT operator Rapid Rail Sdn Bhd said preliminary observations indicated the structural damage to the flyover in the area was believed to be the result of construction work adjacent to the area concerned.

Services on the route between the Masjid Jamek and Bandaraya LRT stations have been discontinued temporarily.

When asked about the possible action against the developer, the minister said the repairs are priority.

“We have to bear the cost of the repairs first, as we cannot afford to wait for the compensation from legal action.

“However, once we get evidence, we reserve the right to take necessary legal action against them,” said Loke. 

He added that he hopes the local authorities in charge of construction will consult the Land Public Transport Agency if their works are near any railway protection zones. – The Vibes, February 22, 2023

Related News

Malaysia / 8mth

Domestic flight capacity increases ahead of Hari Raya - Loke

Malaysia / 9mth

DAP’s July 12 congress: An indication of deeper unease within the party?

Malaysia / 2y

Airlines to refund consumers for flight delays soon, says Anthony Loke

Malaysia / 2y

B1, B2 licences can be upgraded to Class B now, says Anthony Loke

Malaysia / 2y

Anthony Loke’s shortness of breath not related to heart attack, says Lukanisman

Business / 2y

Fresh opportunities for Sabah's sluggish shipping industry as Putrajaya discontinues National Load Centre policy

Spotlight

Malaysia

Anwar receives special recognition as 10,000 Muslims gather in Putrajaya

Malaysia

Video of elderly man being assaulted goes viral on social media

Malaysia

The wide reach of corruption and organised crime in the country

Malaysia

Malaysia pushes to give smaller economies stronger voice in Asia-Pacific trade – Anwar

Malaysia

No tsunami threat to Malaysia after 5.4-magnitude earthquake hits Banda Sea

Malaysia

Who is calling the shots in Negeri Sembilan as Ismail’s position comes under scrutiny?

Opinion

Ayob Khan: When the uniform comes off, the principles remain

Malaysia

MySiren to send emergency alerts to compatible phones nationwide from Nov 29 test

You may be interested

Malaysia

Sabah O&G contracts to local firms surge nearly ninefold to RM3b

Malaysia

Hajiji: GRS has not decided on political cooperation for GE16

Malaysia

Almost half of Malaysians see law enforcement as highly corrupt

Malaysia

Singaporean fugitive wanted for corruption arrested in Johor after four years on the run

Malaysia

Elderly man’s rampage leaves police officer injured in Sungai Besar

Malaysia

Woman killed as Tesla allegedly runs red light and crashes into car in Kulim

Malaysia

Türkiye's four million refugee burden behind rejection of Malaysia's Rohingya request

Malaysia

Federal Government, Sabah and Sarawak continue talks on new special grant formula