Developers of projects delayed pre-pandemic must pay compensation: Zuraida

Exemption only applies to delayed works between March and December last year, says housing minister

Updated 5 years ago · Published on

Developers of projects delayed pre-pandemic must pay compensation: Zuraida
Housing and Local Government Minister Datuk Zuraida Kamaruddin says developers are still required to pay compensation or liquidated ascertained damages to buyers for any delayed projects that were supposed to be completed before March last year. – Bernama pic, February 19, 2021

JOHOR BARU – The exemption for the extension of time (EOT) as stipulated in the Covid-19 Act (Act 829) involving the Housing Development (Control and Licensing) Act 1966 is only applicable to housing projects that were supposed to be completed between March and December last year.

Housing and Local Government Minister Datuk Zuraida Kamaruddin said for any delayed projects that were supposed to be completed before March last year, developers are still required to pay compensation or liquidated ascertained damages to buyers.

“We provide this exemption for Covid-19 from March until December 2020. Only for that period. Other than that, they have to pay compensation.

“However, for delayed projects this year, we can consider (providing exemption) but they must have solid reasons. The consideration is only up to March 2021,” she told a press conference after handing over the keys to house buyers of Taman Seri Molek Perdana Phase 1 and PPR Taman Perling, Johor, here, today.

Zuraida was commenting on whether the exemption for compensation payments allocated in Act 829 is applicable to housing projects that were supposed to be completed before the pandemic hit the country.

The Covid-19 Act involving the Housing Development (Control and Licensing) Act 1966 is part of the Temporary Measures for Reducing the Impact of Coronavirus Disease 2019 (Covid-19) Act 2020, which was passed in the Dewan Rakyat in August last year.

Under the act, developers are given temporary protection for delayed works due to the movement control order since March 18, 2020, and they cannot be sued by buyers or banks for failing to complete their projects according to schedule. – Bernama, February 19, 2021

Related News

Malaysia / 2mth

Penang CM defends move by housing board, says enforcement is last resort

Malaysia / 4mth

Young voters could decide Johor election outcome as parties battle for new electorate

Malaysia / 4mth

PH launches 'Johor For All' manifesto, focuses on jobs, housing and people's well-being

Malaysia / 6mth

Covid-19 cases in Malaysia stable, no deaths recorded this year – MOH

Business / 6mth

Higher diesel prices raise construction costs by as much as 15%

Malaysia / 6mth

PBTs urged to consider rental cuts until year-end

Spotlight

Malaysia

No nation will become poor by helping the poor – Anwar

Malaysia

Negeri Sembilan PH lauds Tuanku Muhriz’s wisdom in handling political crisis

Malaysia

I am not disappointed at not being appointed Menteri Besar – Jalaluddin

Malaysia

DAP demands equal enforcement after three leaders summoned for questioning

Malaysia

Deaf man’s alleged knife attack on disable girlfriend: Court defers charge for sign language interpreter

Malaysia

Negeri Sembilan Exco to meet twice weekly to clear two-month backlog

Malaysia

‘Do not repeat past mistakes,’ Tuanku Muhriz warns new Negeri Sembilan Exco

People

Penang Exco stuck in traffic resorts to video call to greet guests at event

By Ian McIntyre

You may be interested

Malaysia

Budget 2027 passage strengthens Anwar as government cuts new borrowings to RM70b

Malaysia

DAP demands equal enforcement after three leaders summoned for questioning

Malaysia

Eleven foreigners held in Bukit Ceylon raid over NYPD police impersonation scam

Malaysia

Sarawak PRN: All nomination centres closed

Malaysia

Sarawak PRN: GPS clinches 24 seats uncontested

Malaysia

January salaries for Negeri Sembilan civil servants guaranteed amid political uncertainty - Anwar

Malaysia

MACC denies selective investigations, says RM2.1b overspending probe ongoing

Malaysia

EC seeks AGC ruling on possibility of GPS securing Sarawak majority before polling